KMA Splits Delayed Krofrom Market Project into Phases to Speed Up Completion

After years of stalled progress, the Kumasi Metropolitan Assembly has split the Krofrom Market redevelopment into four phases to get work moving again.
The first phase, worth GH¢37 million, was handed over on Friday, November 27, 2026, to NickSeth Construction Company Limited, which is expected to deliver more than 200 shops by November 2027.
Kumasi Mayor Richard Ofori Agyeman Boadi said the phased approach will allow different contractors to work at the same time, rather than waiting for one company to complete the entire project.
He said the remaining smaller phases will also be awarded once documentation is completed.
The project is being financed from the District Assemblies Common Fund earmarked by government for markets under the 24-hour economy programme.
When completed, the redeveloped market is expected to ease congestion in Kumasi by moving hawkers and street traders off the streets into an organised trading centre.
The full facility is planned to include 269 shops and stalls, 3,069 sheds, a fire station and a bus terminal.
Technical Director of NickSeth Construction, Charles Essel, assured the Assembly that the company has the capacity to deliver quality work on schedule, with modern touches and minor adjustments to old structures to meet current standards.