General News

“Second Phase Of Construction Of Central Market Halted”- Local Consultant for Contracta

The local consultant for Contracta, the company in charge of the redevelopment of the Kumasi Central Market has announced a halt in the phase two of the project.

“We have withheld work in the phase two, as you know, we are in a business season, November and December are just around the corner and so people have to conduct their businesses. The emergence of COVID-19 has brought many businesses to a standstill”

He added that the traders will therefore be allowed to transact their businesses in the market within this season but will have to move right after that for construction to resume at the site at the beginning of 2021

“After Christmas… we will resume work to make the market a better place for the traders to transact their businesses”, he added

He explained a halt in the second phase which started in May and was scheduled to be completed within 48 months, according to graphic online, will be lengthened but the availability of both human and material resources will speed up the work

“The duration will extend… all equipment and materials are ready. We will sometimes work 24hours, a batch will work on shift during the day and another at night”, he revealed.

Source: Opemsuo FM/ Hajara Fuseini